Lopdell House / Te Uru
Lopdell House / Te Uru
Situation: Historic building being extensively renovated and upgraded to modern standards. An additional gallery was constructed on an adjorning steep site.
Challenge: Waterproofing of the basement was critical as sensitive artwork wuld be stored inside the building. In addition, creating an insulated deck on top of the historic building was required.
Solution: The existing roof was stripped off the building. A Nuratherm warm roof system was installed including two layers of Nuraply membrane. Deck pedestals were laid over the Nuratherm to support the removable tile system.

The walls and floor of the new gallery were encased with Nuraply 3PT and 3PTM. Fully bonded to the building, they proved their worth when the soil moved whilst the building was being constructed.